Northern Walnut Creek Trail Phase 1A – Meet the Contractor
Date: March 6, 2018
Covenant United Methodist Church
4410 Duval Road, 6:30 p.m.
Austin, Texas 78727
Project Description
This project is the final piece of the Northern Walnut Creek Trail Project that extends from Balcones District Park to Walnut Creek Metropolitan Park. The project will construct approximately 2,030 feet of ten-foot-wide concrete trail with two-foot shoulders from Amherst Drive through Balcones District Park to the existing segment on the south side of the baseball field in the park. It will also include 200 feet of sidewalk, retaining walls to maintain an acceptable slope, storm water facilities to accommodate existing drainage patterns, and will have environmental protections to safeguard existing protected species and sensitive areas.
Project Schedule –The project is anticipated to begin in mid-March and will take about 6 months to complete.
What to expect during construction
–The project staging area will be in Balcones District park off Scribe Lane.
–There are two construction entrances on this project to expedite construction. –The first is off Amherst Drive and the second will be located off Scribe Drive.
–Temporary access to baseball field will temporarily be off Stoney Drive.
–The trail will be closed once construction begins until further notice.
Communication Plan
–Monthly Status Updates via email & Public Works Department website https://www.austintexas.gov/page/walnut-creek-trail-system
–Social media, updates posted as needed on NextDoor and City of Austin Public Works Facebook page